Permits/Inspections.  During the month of April, two single family home permits were issued for the Northmark Subdivision on Buford Highway near Woodward Mill Road, each averaging 2,900 square feet. Five townhome permits were also issued in Northmark, with an average of 2,300 square feet each. A rezoning request is scheduled for a public hearing during …... Read More Management Report – May 2022

Public Projects Construction Update – April 2022

Project Updates, Public Works |

Sugar Hill Greenway   We now have a paved trail in the segment of trail between Peachtree Industrial and Level Creek Road.  TriScapes, the city’s contractor is finalizing the trail shoulders and getting any remaining disturbed areas stabilized with mulch.  One other key milestone achieved in the last week of March was the delivery of …... Read More Public Projects Construction Update – April 2022