Project Updates, Public Works |

Ridge Lake Park.     Construction is fast approaching the finish line for the new park that will be on 22 acres the city owns off of Highway 20 (5494 Cumming Highway). Consisting of a parking area, rest room building with covered seating area, a dog park, pond improvements and trails; it will be the newest place to relax, enjoy nature, and unwind. Groundbreaking was held on November 29th, 2022. Many of the amenities in the park were suggested by the public during open houses that we held in 2017 and 2018.

Grading work is almost finished. The building is dried in and work is beginning on interior equipment and finishes. Also, the dam repair for the lower and upper pond are well under way and should be complete soon. The septic system has been installed as well as the dog park fence. Work has begun on the decel lane on Hwy 20. The parking area and driveway should be completed soon as well. Look for an August 2023 completion.

Bowl Pond Improvements.    Intended to make this amenity more stable and usable, these improvements include replacing the failed outlet that regulates pond water level and prevents flooding. Also, a new area for events, congregating or just relaxing will be installed. It will also have a new parking area that will serve as a load-in area for concerts and performances.

Construction is only days away from being complete. The walls and columns that define the terraces are built. The parking area has been poured and work on the pervious pavers has been completed. A few punch list items remain, mostly having to do with landscaping.  This project should be completed by the middle of August.

Alton Tucker Blvd Extension.  The design and bid phases of this project are in the rear view mirror and we have awarded the project to Ohmshiv Construction, LLC. This project will improve the intersection of Level Creek Rd and West Broad Street, as well as extending Alton Tucker to Highway 20 at the east end of the E Center property. This project should be completed by the end of 2024. Ohmshiv will mobilize in the next week or so. Work will begin on the road coming from Highway 20 to the E Center drive.

Street Paving and Repair.     The contract has been awarded to Georgia Paving for the 2022,2023 LMIG street project. We received bids from 8 companies to repave and repair 23 streets, a parking lot and a cemetery driveway.

The streets to be addressed are:

Road Name From To
Brookdale Dr Hillcrest cul de sac
Primrose Park Rd Blossom Brook Ct city limits
Primrose Park Ct Primrose Park Rd cul de sac
Summer Creek Ct Primrose Park Rd cul de sac
Blossom Brook Dr Primrose Park Rd Avalon Creek Rd
Avalon Creek Rd Phase Line cul de sac
Roberts Run Cove Roberts Rd cul de sac
Spring Hill Dr Level Creek Rd Whitehead Rd
Pinecrest Dr PIB end
Church St Level Creek Rd W Broad St
W Broad St Alton Tucker Blvd Nelson Brogdon Blvd
Arbor View Way Underhill Ct cul de sac
Pine Branch Cir Arbor View Way cul de sac
Pine Branch Ct Arbor View Way cul de sac
Under Hill Ln Arbor View Way cul de sac
Oak Grove Dr Level Creek Rd end
Avonley Creek Dr Old Cumming Hwy Avonley Creek Trace
Kyle Trace Ct. Avonley Creek Dr. cul de sac
Glencora Close Avonley Creek Dr. cul de sac
Avonley Creek Trc Avonley Creek Dr. cul de sac
Starwind Way Avonley Creek Dr. cul de sac
Paliser Trc Avonley Creek Trace cul de sac
Cemetery Driveways Various
Wintersweet Way Hwy 20 Silverberry Ln

Paving has been completed on the highlighted streets above. Work on the downtown streets should be done towards the end of August. Anticipated completion for this project is October 31.

Highway 20 Pedestrian Bridge   

Design work is well underway. The general layout, size and construction materials have been decided. Next will be the aesthetics and the permitting with GDOT.  Once those parameters are set, we can advertise for a construction partner.

Anticipated completion date is early 2025.

 

Downtown Greenway/LCI Project   

This project is funded by a grant from the Federal Highway Administration, so the process is a little different. The first step is to prepare a Request for Qualifications (RFQ) from pre-qualified design firms. We are working on that now, and once approved by GDOT, we will be able to advertise for a design partner. It will connect PIB/20 to Alton Tucker and then on back to Highway 20. The timeline will be determined once we have the design finished.

Whitehead Road Sidewalks 

This project is in the beginning stages of design and Right of Way (ROW) acquisition. Once those items are completed, we will advertise for a construction contractor. We anticipate a mid 2024 start date.