RFP #25-017 Riverlands Hike Bike Trail

Bids & RFPs, Bids & RFPs Closed |

CLOSED... Read More → RFP #25-017 Riverlands Hike Bike Trail

Public Project Construction Update – June 2026

Project Updates, Public Works |

Highway 20 Pedestrian Bridge  Bridge design, permitting and bid phases are complete.  The contract has been awarded to Ohmshiv Construction, LLC. Recently, All beams and spans are in place. The deck to the bridge has been poured and work has shifted to constructing the parapet walls. The ones across highway 20 have been poured and the ones on the E Center side have been formed and will be poured this week. Downtown …... Read More → Public Project Construction Update – June 2026

Public Project Construction Update – May 2026

Project Updates, Public Works |

  Highway 20 Pedestrian Bridge Bridge design, permitting and bid phases are complete.  The contract has been awarded to Ohmshiv Construction, LLC. Recently, The span beams across Hwy 20 were installed earlier this month. Work has shifted to the E Center side. Wall 1 is nearing completion. They are pouring the bearing pads for remaining …... Read More → Public Project Construction Update – May 2026

Public Project Construction Update – April 2026

Project Updates, Public Works |

Highway 20 Pedestrian Bridge Bridge design, permitting and bid phases are complete.  The contract has been awarded to Ohmshiv Construction, LLC. Recently, construction of  the pier tops was started and they should be completed  by the end of the week. Work is nearing completion on MSE wall 2 at the end of the ramp. The next major part of the project, installing the span beams over Hwy 20, is scheduled for the middle of May during the overnight hours. Work should begin soon …... Read More → Public Project Construction Update – April 2026

RFP # 26-002.2 ROOSEVELT COLLECTION AFFORDABLE HOUSING

Bids & RFPs, Bids & RFPs Closed |

CLOSED... Read More → RFP # 26-002.2 ROOSEVELT COLLECTION AFFORDABLE HOUSING

RFP 26-004 Ridge Lake Park Phase III

Bids & RFPs, Bids & RFPs Closed |

CLOSED... Read More → RFP 26-004 Ridge Lake Park Phase III

Public Project Construction Update – January 2026

Project Updates, Public Works |

Highway 20 Pedestrian Bridge Bridge design, permitting and bid phases are complete.  The contract has been awarded to Ohmshiv Construction, LLC. A pre-construction meeting was held on November 19, 2024. Shop Drawings for the ramp portion of the bridge on the South side are in process (MSE Wall #1). When complete, construction of the ramps …... Read More → Public Project Construction Update – January 2026

IFB # 26-001– ROAD RESURFACING & REPAIRS ON VARIOUS CITY STREETS

Bids & RFPs, Bids & RFPs Closed |

CLOSED... Read More → IFB # 26-001– ROAD RESURFACING & REPAIRS ON VARIOUS CITY STREETS

Public Project Construction Update – December 2025

Project Updates, Public Works |

2025 Completed Projects:Road Repairs & Repaving A total of 4.7 miles of roads were patched and repaved. $1,326,607 of SPLOST & State grant funds were used to complete repairs to 23 neighborhood streets. PIB East and Spring Hill Sidewalks 1694 feet of sidewalk on PIB and 588 feet on Spring Hill. at a cost of …... Read More → Public Project Construction Update – December 2025

RFQ 26-002 – Roosevelt Collection

Bids & RFPs, Bids & RFPs Closed |

CLOSED... Read More → RFQ 26-002 – Roosevelt Collection

Close Search Window
↑