Sugar Hill vs. AGL Rates – June 2022

Rate Comparison |

... Read More Sugar Hill vs. AGL Rates – June 2022

Public Projects Construction Update – April 2022

Project Updates, Public Works |

Sugar Hill Greenway   We now have a paved trail in the segment of trail between Peachtree Industrial and Level Creek Road.  TriScapes, the city’s contractor is finalizing the trail shoulders and getting any remaining disturbed areas stabilized with mulch.  One other key milestone achieved in the last week of March was the delivery of …... Read More Public Projects Construction Update – April 2022

Public Projects Construction Update – March 2022

Project Updates, Public Works |

Sugar Hill Greenway   We have pavement in the segment of trail between Peachtree Industrial and Level Creek Road.  TriScapes, the city’s contractor is working to grade the shoulders and get any remaining disturbed areas stabilized with mulch.  One other key milestone achieved in the last week of the month is the delivery of Bridge …... Read More Public Projects Construction Update – March 2022

Sugar Hill vs. AGL Rates – February 2022

Rate Comparison |

... Read More Sugar Hill vs. AGL Rates – February 2022

Public Projects Construction Update – January 2022

Project Updates, Public Works |

Sugar Hill Greenway   TriScapes Construction (TSI) is making progress during the drier weeks of January on the segment of trail between Peachtree Industrial and Level Creek Road.  Paving is set to get underway later in February or early March, depending on temperatures as this section is composed of asphalt concrete pavement.  Short supplies, short …... Read More Public Projects Construction Update – January 2022

Public Projects Construction Update – December 2021

Project Updates, Public Works |

Roadway Repairs & Resurfacing (LMIG) The paving of all streets on the 2020-2021 LMIG project list is complete. In Frontier Forest, there are a few valve and manhole covers that need to be adjusted and the striping needs to be completed to close out this project. These streets were completed in this year’s contract: columns …... Read More Public Projects Construction Update – December 2021

Public Projects Construction Update – November 2021

Project Updates, Public Works |

Sugar Hill Greenway   TriScapes Construction (TSI) continues construction on the 3rd & 4th segmentS of their contract that take the proposed trail from Level Creek Road westward to Whitehead Road.  More specifically, they are working on installation of a series of boardwalk segments in the environmentally sensitive areas.  These segments follow the old Georgia …... Read More Public Projects Construction Update – November 2021

Public Projects Construction Update – October 2021

Project Updates, Public Works |

Sugar Hill Greenway TriScapes Construction (TSI) is currently focusing attention on the 3rd segments of their contract that take the proposed trail from Level Creek Road westward to Whitehead Road.  More specifically, they are working on installation of a series of boardwalk segments in the environmentally sensitive areas.  These segments follow the old Georgia DOT …... Read More Public Projects Construction Update – October 2021

Public Projects Construction Update – August 31st

Project Updates, Public Works |

Sugar Hill Greenway.   TriScapes Construction (TSI) is currently focusing attention on the 3rd segments of their contract that take the proposed trail from Level Creek Road westward to Whitehead Road.  More specifically, they are working on installation of a series of boardwalk segments in the environmentally sensitive areas.  These segments follow the old Georgia …... Read More Public Projects Construction Update – August 31st

Sugar Hill vs. AGL Rates – August 2021

Rate Comparison |

... Read More Sugar Hill vs. AGL Rates – August 2021

Close Search Window