Public Project Construction Update – October, 2024

Project Updates, Public Works |

Highway 20 Pedestrian Bridge.  Bridge design is complete. The layout, size and construction materials have been selected. The permitting process is also complete and we have it in hand from GDOT.  The project has been awarded to Ohmshiv Construction, LLC. Anticipated completion date is the end of 2025. Downtown Greenway/LCI Project. The trail connection from …... Read More Public Project Construction Update – October, 2024

Public Project Construction Update – September, 2024

Project Updates, Public Works |

Highway 20 Pedestrian Bridge. Bridge design is complete. The general layout, size and construction materials have been selected. The permitting process is also complete and we have it in hand from GDOT.  We advertised for a construction partner and received three bids that we are evaluating now. Anticipated completion date is the end of 2025. …... Read More Public Project Construction Update – September, 2024

Public Project Construction Update – July 2024

Project Updates, Public Works |

Alton Tucker Blvd Extension.  This project’s objective was to improve the intersection of Level Creek Rd and West Broad Street, as well as extend Alton Tucker to Highway 20 at the east end of the E Center property, connecting the downtown to Highway 20. Paving, striping, and signal installation has been completed. A stamped asphalt …... Read More Public Project Construction Update – July 2024

Public Project Construction Update – June 2024

Project Updates, Public Works |

Alton Tucker Blvd Extension.  This project’s objective is to improve the intersection of Level Creek Rd and West Broad Street, as well as extending Alton Tucker to Highway 20 at the east end of the E Center property. Paving is complete and signal installation is finished as well. A stamped asphalt decorative application at the …... Read More Public Project Construction Update – June 2024

Public Project Construction Update – May 2024

Project Updates, Public Works |

Alton Tucker Blvd Extension.  This project’s objective is to improve the intersection of Level Creek Rd and West Broad Street, as well as extending Alton Tucker to Highway 20 at the east end of the E Center property. Paving is complete and signal installation should be finished this week. A stamped asphalt decorative application at …... Read More Public Project Construction Update – May 2024

Public Project Construction Update – April, 2024

Project Updates, Public Works |

Alton Tucker Blvd Extension.  This project’s objective is to improve the intersection of Level Creek Rd and West Broad Street, as well as extending Alton Tucker to Highway 20 at the east end of the E Center property. The alignment, concrete, landscaping work for this project are complete. Brick paver installation is 90% complete. The …... Read More Public Project Construction Update – April, 2024

Public Project Construction Update – March, 2024

Project Updates, Public Works |

Alton Tucker Blvd Extension. This project’s objective is to improve the intersection of Level Creek Rd and West Broad Street, as well as extending Alton Tucker to Highway 20 at the east end of the E Center property. The alignment and concrete work for this project are substantially complete. Sidewalk brick paver installation Is 90% …... Read More Public Project Construction Update – March, 2024

Public Project Construction Update – February 2024

Project Updates, Public Works |

Alton Tucker Blvd Extension.     This project’s objective is to improve the intersection of Level Creek Rd and West Broad Street, as well as extending Alton Tucker to Highway 20 at the east end of the E Center property. The alignment and concrete work for this project are mostly complete. Brick paver installation will begin next. …... Read More Public Project Construction Update – February 2024

Public Project Construction Update – January 2024

Project Updates, Public Works |

Alton Tucker Blvd Extension.     This project’s objective is to improve the intersection of Level Creek Rd and West Broad Street, as well as extending Alton Tucker to Highway 20 at the east end of the E Center property. The grading and gravel base for the extension to Highway 20 are substantially complete. New drainage structures, …... Read More Public Project Construction Update – January 2024

Public Project Construction Update – December 2023

Project Updates, Public Works |

Alton Tucker Blvd Extension.   This project’s objective is to improve the intersection of Level Creek Rd and West Broad Street, as well as extending Alton Tucker to Highway 20 at the east end of the E Center property. The grading and gravel base for the extension to Highway 20 are substantially complete. New drainage structures, …... Read More Public Project Construction Update – December 2023

Close Search Window
Skip to content