Public Projects Construction Update – January 21st

Project Updates, Public Works |

Sugar Hill Greenway.  Construction is substantially complete. Sugar Hill Greenway – Phase 1B (OSC / PIB Portion looking North) – Handrail installed. (Jan. 20, 2021) Greenway Trail – looking north near Shiv Mandir entrance (Jan. 20, 2021) TriScapes Construction (TSI) has initiated construction on the major segment of greenway trail construction connecting downtown with EE …... Read More Public Projects Construction Update – January 21st

Public Projects Construction Update – December 11th

Project Updates, Public Works |

Sugar Hill Greenway.  Construction is substantially complete on the Ohmshiv Construction (OSC) contract on Whitehead Road AND Peachtree Industrial Boulevard.  The contractor and project management team completed a punch list inspection on December 3 and a short list of items for correction have been generated.  Overall, the project has turned out well with a very …... Read More Public Projects Construction Update – December 11th

Public Projects Construction Update – November 16th

Project Updates, Public Works |

Sugar Hill Greenway.  Construction is substantially complete on the Ohmshiv Construction (OSC) contract on Whitehead Road while the PIB segment is wrapping up with guardrail relocation.  The large retaining wall required at the Shiv Mandir entrance was completed in October and much of the trail construction completed at that time.  Drainage modifications and punch list …... Read More Public Projects Construction Update – November 16th

Public Projects Construction Update – September 11th

Project Updates, Public Works |

Sugar Hill Greenway.  Work is converging on a completion point on the Whitehead Road portion of the greenway.  A drainage structure still needs to be installed along with backfilling as well as grassing and cleanup before this segment is complete.  The Peachtree Industrial segment is still at the 80% point with a retaining wall portion …... Read More Public Projects Construction Update – September 11th

Public Projects Construction Update – August 21st

Project Updates, Public Works |

5243 Nelson Brogdon Blvd. (former Citgo) Demolition.  Convenience store building at the property address 5243 Nelson Brogdon Boulevard has been demolished under court-order, having been determined to be an unsafe structure.   Sugar Hill Greenway.  Work is still progressing slowly on the Peachtree Industrial portion (Phase 1B) of the greenway, with 90 of the trail …... Read More Public Projects Construction Update – August 21st

Public Projects Construction Update – July 31st

Project Updates, Public Works |

E Center.  Installation of a new epoxy floor coating for the common areas of the entire building is nearing the finish line with another coat, polishing, wall base and cleanup to complete the new look.  New South Construction completed leak repairs on the eastern upper pool fountain last week. New flooring in the E Center …... Read More Public Projects Construction Update – July 31st

Public Projects Construction Update – July 13th

Project Updates, Public Works |

E Center.  Red Clay Interactive (RCI), a local marketing firm, has completed their buildout and are waiting to schedule move-in.  Installation of a new epoxy floor coating for the common areas of the entire building is nearing the finish line with another coat, polishing, wall base and cleanup to complete the new look.  In addition, …... Read More Public Projects Construction Update – July 13th

Public Projects Construction Update – June 18th

Project Updates, Public Works |

E Center.  Red Clay Interactive (RCI), a local marketing firm, has completed their buildout and are waiting to schedule move-in.  Installation of a new epoxy floor coating for the common areas of the entire building is nearing the finish line with another coat, polishing, wall base and cleanup to complete the new look.  In addition, …... Read More Public Projects Construction Update – June 18th

Public Projects Construction Update – May 29th

Project Updates, Public Works |

E Center.  Red Clay Interactive (RCI), a local marketing firm, is at the finish line for their new offices in suites 209 and 211 at the E Center.  They have their certificate of occupancy and are gearing up to move in and get up and running in Sugar Hill.  Installation of a new epoxy floor …... Read More Public Projects Construction Update – May 29th

Public Projects Construction Update – May 1st

Project Updates, Public Works |

E Center.  Red Clay (RCI) is nearing completion of their office buildout in spaces 209 and 211—flooring and some remaining tasks outstanding.  Installation of a new epoxy floor coating for the common areas of the entire building is being completed as well during the recent pandemic-related closures. Veterans Memorial Relocation.  Punch list work continues on …... Read More Public Projects Construction Update – May 1st

Close Search Window
Skip to content