PUBLIC PROJECT CONSTRUCTION UPDATE – August 2025

Project Updates, Public Works |

PUBLIC PROJECT CONSTRUCTION UPDATE – August 28, 2025   2025 LMIG Street Repair/Repaving. The streets on the original LMIG request are substantially complete. A second round of funds was approved by the state and the streets for that list will be started September 1. All streets will receive patching, milling and asphalt overlay. The streets …... Read More PUBLIC PROJECT CONSTRUCTION UPDATE – August 2025

Public Project Construction Update – July 2025

Project Updates, Public Works |

PUBLIC PROJECT CONSTRUCTION UPDATE – July 31, 2025   2025 LMIG Street Repair/Repaving The streets on the original LMIG request are substantially complete. Some punch list items are being addressed now. A second round of state funds was approved by the Governor in the spring and repairs to those streets should start September 1. All streets will …... Read More Public Project Construction Update – July 2025

RFB 25-005– Ridge Lake Park Playground

Bids & RFPs, Bids & RFPs Closed |

CLOSED... Read More RFB 25-005– Ridge Lake Park Playground

IFB 25-001– Sugar Hill Cemetery Fencing Improvement

Bids & RFPs, Bids & RFPs Closed |

CLOSED... Read More IFB 25-001– Sugar Hill Cemetery Fencing Improvement

Park Maintenance – Full-Time Job Opportunity

Employment, Employment Opportunities, Uncategorized |

POSITION TITLE: Park Maintenance DEPARTMENT: Parks & Recreation REPORTS TO: Parks Manager EMPLOYMENT STATUS: Full Time: Hours may vary and include weekdays, and weekends POSITION SUMMARY: This full-time position will be responsible for performing routine maintenance of grounds such as mowing grass, picking up trash, and basic equipment maintenance. This position requires the incumbent to …... Read More Park Maintenance – Full-Time Job Opportunity

PUBLIC PROJECT CONSTRUCTION UPDATE – APRIL 2025

Uncategorized |

2025 LMIG Street Repair/Repaving  Council approved the contract for 2025 LMIG Street Repair/Repaving at their March meeting. A pre-construction meeting was held on March 25th where a notice to proceed was issued. Work has begun In Lakefield Forest. Completion is scheduled for November 30th.  The highlighted streets below have been milled, crack sealed, patched and …... Read More PUBLIC PROJECT CONSTRUCTION UPDATE – APRIL 2025

PUBLIC PROJECT CONSTRUCTION UPDATE – March 2025

Project Updates, Public Works |

2025 LMIG Street Repair/Repaving. Council approved the contract for 2025 LMIG Street Repair/Repaving at their March meeting. A pre-construction meeting was held on March 25th where a notice to proceed was issued. The notice to  proceed issued for April 21st. The contractor, triple R paving, when they will begin their schedule to repair and resurface …... Read More PUBLIC PROJECT CONSTRUCTION UPDATE – March 2025

Public Project Construction Update – February 2025

Project Updates, Public Works |

2025 LMIG Street Repair/Repaving.  On February 6th we received 13 bids to complete pavement repairs and resurfacing on 15 streets. We will be presenting the results along with a recommendation for awarding the construction contract at the March City Council meeting to the low bidder. Work will begin shortly after that and should be completed …... Read More Public Project Construction Update – February 2025

Sugar Hill vs. AGL Rates – February 2025

Gas Utility, Rate Comparison |

... Read More Sugar Hill vs. AGL Rates – February 2025