Public Projects Construction Update – January 2022

Project Updates, Public Works |

Sugar Hill Greenway   TriScapes Construction (TSI) is making progress during the drier weeks of January on the segment of trail between Peachtree Industrial and Level Creek Road.  Paving is set to get underway later in February or early March, depending on temperatures as this section is composed of asphalt concrete pavement.  Short supplies, short …... Read More Public Projects Construction Update – January 2022

Public Projects Construction Update – December 2021

Project Updates, Public Works |

Roadway Repairs & Resurfacing (LMIG) The paving of all streets on the 2020-2021 LMIG project list is complete. In Frontier Forest, there are a few valve and manhole covers that need to be adjusted and the striping needs to be completed to close out this project. These streets were completed in this year’s contract: columns …... Read More Public Projects Construction Update – December 2021

Public Projects Construction Update – November 2021

Project Updates, Public Works |

Sugar Hill Greenway   TriScapes Construction (TSI) continues construction on the 3rd & 4th segmentS of their contract that take the proposed trail from Level Creek Road westward to Whitehead Road.  More specifically, they are working on installation of a series of boardwalk segments in the environmentally sensitive areas.  These segments follow the old Georgia …... Read More Public Projects Construction Update – November 2021

Public Projects Construction Update – October 2021

Project Updates, Public Works |

Sugar Hill Greenway TriScapes Construction (TSI) is currently focusing attention on the 3rd segments of their contract that take the proposed trail from Level Creek Road westward to Whitehead Road.  More specifically, they are working on installation of a series of boardwalk segments in the environmentally sensitive areas.  These segments follow the old Georgia DOT …... Read More Public Projects Construction Update – October 2021

Public Projects Construction Update – August 31st

Project Updates, Public Works |

Sugar Hill Greenway.   TriScapes Construction (TSI) is currently focusing attention on the 3rd segments of their contract that take the proposed trail from Level Creek Road westward to Whitehead Road.  More specifically, they are working on installation of a series of boardwalk segments in the environmentally sensitive areas.  These segments follow the old Georgia …... Read More Public Projects Construction Update – August 31st

Public Projects Construction Update – July 23rd

Project Updates, Public Works |

Sugar Hill Greenway. TriScapes Construction (TSI) is currently focusing attention on the 2nd and 3rd sements of their contract that take the proposed trail from Peachtree Industrial westward to Whitehead Road.  These segments follow the old Georgia DOT right-of-way for the outer perimeter project and follow many of the most scenic places in the city. …... Read More Public Projects Construction Update – July 23rd

Public Projects Construction Update – June 30th

Project Updates, Public Works |

Sugar Hill Greenway. TriScapes Construction (TSI) is currently focusing attention on the 2nd and 3rd sements of their contract that take the proposed trail from Peachtree Industrial westward to Whitehead Road.  These segments follow the old Georgia DOT right-of-way for the old outer perimeter project and are in some of the most scenic places in …... Read More Public Projects Construction Update – June 30th

Public Projects Construction Update – May 14th

Project Updates, Public Works |

Sugar Hill Greenway. Sugar Hill Greenway Map TriScapes Construction (TSI) has just completed the paving of the segment of trail through EERobinson Park (North) and will be finishing the shoulders and tie-ins at each end.  The public is encouraged to stay off the trails until the barriers are removed and it is safe to use.  …... Read More Public Projects Construction Update – May 14th

Public Projects Construction Update – April 12th

Project Updates, Public Works |

Sugar Hill Greenway. Sugar Hill Greenway Map TriScapes Construction (TSI) is substantially complete for the 2,000 linear feet of new concrete trail along Level Creek Road. TSI is now working on the asphalt portions of the trail through the old EE Robinson Park (North), having graded and placed gravel base for the section in the …... Read More Public Projects Construction Update – April 12th

Public Projects Construction Update – February 12th

Project Updates, Public Works |

Sugar Hill Greenway. Sugar Hill Greenway Map TriScapes Construction (TSI) is well underway with the major downtown segment of greenway trail construction connecting downtown with EE Robinson Park.  TSI has completed concrete paving on about 2,000 linear feet of new trail along Level Creek Road.  The TSI contract will encompass about 4 and a half …... Read More Public Projects Construction Update – February 12th