Project Updates, Public Works |

E Center.  Installation of a new epoxy floor coating for the common areas of the entire building is nearing the finish line with another coat, polishing, wall base and cleanup to complete the new look.  New South Construction completed leak repairs on the eastern upper pool fountain last week.

New flooring in the E Center

Veterans Memorial Relocation.  There are a few replacement items and documents the general contractor is waiting on to close out the contract.  Several warranty items have been corrected and the fountain, eternal flame, and other systems are working properly.

2019 Bowl Improvements.  Project has been closed out and is complete.

Sugar Hill Greenway.  Work the last two weeks of the month on the Peachtree Industrial portion (Phase 1B) of the greenway, completing another 850 feet from the EE Robinson North entrance almost to the new Shiv Mandir site.  The plans for the balance of Phase 1 has been approved for construction and work is expected to begin in late August or early September.  This project is funded through a combination of city and county SPLOST funds by way of an intergovernmental agreement.

North end of the PIB section (looking south toward Shiv Mandir)

Sugar Hill Greenway – Phase 1B (PIB Portion)

Sugar Hill Greenway – Phase 1 Construction is right around the corner.

 Gary Pirkle Park Field Expansion.  Project is about to gear up for construction with the contract awarded at the July Council meeting.  A pre-construction meeting is being scheduled for mid-August and construction to follow late summer.

Art/History Room Buildout at Broadstone.  Bids will be received until next Thursday.

Level Creek / Alton Tucker. Right-of-way acquisition is underway and will parallel the final construction and bid documents phase.

Gold Mine Park.  Project is ready for the bid phase.

 

 

Close Search Window