Public Projects Construction Update – February 12th

Project Updates, Public Works |

Sugar Hill Greenway. Sugar Hill Greenway Map TriScapes Construction (TSI) is well underway with the major downtown segment of greenway trail construction connecting downtown with EE Robinson Park.  TSI has completed concrete paving on about 2,000 linear feet of new trail along Level Creek Road.  The TSI contract will encompass about 4 and a half …... Read More Public Projects Construction Update – February 12th

Sugar Hill vs. AGL Rates – January 2021

Rate Comparison |

... Read More Sugar Hill vs. AGL Rates – January 2021

Public Projects Construction Update – January 21st

Project Updates, Public Works |

Sugar Hill Greenway.  Construction is substantially complete. Sugar Hill Greenway – Phase 1B (OSC / PIB Portion looking North) – Handrail installed. (Jan. 20, 2021) Greenway Trail – looking north near Shiv Mandir entrance (Jan. 20, 2021) TriScapes Construction (TSI) has initiated construction on the major segment of greenway trail construction connecting downtown with EE …... Read More Public Projects Construction Update – January 21st

Public Projects Construction Update – December 11th

Project Updates, Public Works |

Sugar Hill Greenway.  Construction is substantially complete on the Ohmshiv Construction (OSC) contract on Whitehead Road AND Peachtree Industrial Boulevard.  The contractor and project management team completed a punch list inspection on December 3 and a short list of items for correction have been generated.  Overall, the project has turned out well with a very …... Read More Public Projects Construction Update – December 11th

Sugar Hill vs. AGL Rates – November 2020

Rate Comparison |

... Read More Sugar Hill vs. AGL Rates – November 2020

Public Projects Construction Update – November 16th

Project Updates, Public Works |

Sugar Hill Greenway.  Construction is substantially complete on the Ohmshiv Construction (OSC) contract on Whitehead Road while the PIB segment is wrapping up with guardrail relocation.  The large retaining wall required at the Shiv Mandir entrance was completed in October and much of the trail construction completed at that time.  Drainage modifications and punch list …... Read More Public Projects Construction Update – November 16th

Sugar Hill vs. AGL Rates – October 2020

Rate Comparison |

... Read More Sugar Hill vs. AGL Rates – October 2020

Sugar Hill vs. AGL Rates – September 2020

Rate Comparison |

... Read More Sugar Hill vs. AGL Rates – September 2020

Public Projects Construction Update – September 11th

Project Updates, Public Works |

Sugar Hill Greenway.  Work is converging on a completion point on the Whitehead Road portion of the greenway.  A drainage structure still needs to be installed along with backfilling as well as grassing and cleanup before this segment is complete.  The Peachtree Industrial segment is still at the 80% point with a retaining wall portion …... Read More Public Projects Construction Update – September 11th

Sugar Hill vs. AGL Rates – August 2020

Rate Comparison |

... Read More Sugar Hill vs. AGL Rates – August 2020