Sugar Hill vs. AGL Rates – May 2020

Rate Comparison |

... Read More Sugar Hill vs. AGL Rates – May 2020

Management Report – May 2020

City Managers Office, Management Reports |

PLANNING AND DEVELOPMENT One permit was issued in the month of April for a 2,723 square feet single-family home.  A remodel permit was also issued for a dental office located in building C at 4300 Westbrook Road.  A certificate of occupancy was issued for a chiropractic office located in building E at 4300 Westbrook Road. …... Read More Management Report – May 2020

Public Projects Construction Update – May 1st

Project Updates, Public Works |

E Center.  Red Clay (RCI) is nearing completion of their office buildout in spaces 209 and 211—flooring and some remaining tasks outstanding.  Installation of a new epoxy floor coating for the common areas of the entire building is being completed as well during the recent pandemic-related closures. Veterans Memorial Relocation.  Punch list work continues on …... Read More Public Projects Construction Update – May 1st

IFB 20-007 Gary Pirkle Park Field Improvements

Bids & RFPs, Bids & RFPs Closed |

AWARDED: Advanced Sports Group (Kennesaw) $1,119,745.10 BID RESULTS: (PDF) IFB 20-007 BID TABULATION SHEET... Read More IFB 20-007 Gary Pirkle Park Field Improvements

Sugar Hill vs. AGL Rates – April 2020

Rate Comparison |

... Read More Sugar Hill vs. AGL Rates – April 2020

Management Report – April 2020

City Managers Office, Management Reports |

PLANNING AND DEVELOPMENT This spring, the city will be initiating work on a plan for future phases of the Sugar Hill Greenway, including a feasibility analysis for crossing over Highway 20 and designing other improvements to pedestrian infrastructure and amenities along Highway 20. Under the Atlanta Regional Commission’s (ARC) Livable Center’s Initiative (LCI) program, the …... Read More Management Report – April 2020

IFB 20-016 Hillcrest Tract Sale of Property

Bids & RFPs, Bids & RFPs Closed |

View Full RFP: Legal Ad - Hillcrest Properties Final View Bid Form: Bid Form IFB 20-016 Hillcrest IFB 20-016 - Addendum 1 20-016 Bid Tabulation... Read More IFB 20-016 Hillcrest Tract Sale of Property

Public Projects Construction Update – April 9th

Project Updates, Public Works |

E Center.  Red Clay (RCI) is underway with their office buildout in spaces 209 and 211 with walls constructed and electrical rough-in being completed.  Installation of a new epoxy floor coating for the common areas is being completed now during the recent pandemic-related closures. Veterans Memorial Relocation.  The sign vendor has been working this week …... Read More Public Projects Construction Update – April 9th

Public Projects Construction Update – March 30th

Project Updates, Public Works |

E Center.  Red Clay (RCI) is underway with their office buildout in spaces 209 and 211.  New South has completed the refinishing of the water feature pools and restarted the system.  Final adjustments will be required to provide the right rate of flow since its last operation last Fall. Installation of a new epoxy floor …... Read More Public Projects Construction Update – March 30th

Public Projects Construction Update – March 20th

Project Updates, Public Works |

E Center.  Red Clay (RCI) is preparing to resubmit for a permit for their office buildout in spaces 209 and 211 and has requested a pre-construction meeting for March 25.  New South was out on site this week working on the diamond brite waterproofing finish for the lower pools.  The coat was installed on the …... Read More Public Projects Construction Update – March 20th