Permits/Inspections. During the month of April, two single family home permits were issued for the Northmark Subdivision on Buford Highway near Woodward Mill Road, each averaging 2,900 square feet. Five townhome permits were also issued in Northmark, with an average of 2,300 square feet each. A rezoning request is scheduled for a public hearing during …...Read More →Management Report – May 2022
Sugar Hill Greenway We now have a paved trail in the segment of trail between Peachtree Industrial and Level Creek Road. TriScapes, the city’s contractor is finalizing the trail shoulders and getting any remaining disturbed areas stabilized with mulch. One other key milestone achieved in the last week of March was the delivery of …...Read More →Public Projects Construction Update – April 2022
Permits/Inspections. During the month of March, three single family home permits were issued for the Northmark Subdivision, each averaging 2,872 square feet. The CO for Jersey Mike’s Subs (adjacent to Publix) was issued during the month of March, and they are now open for business. The new Brogdon Distribution Center at 783 Brogdon Road is …...Read More →Management Report – April 2022
Sugar Hill Greenway We have pavement in the segment of trail between Peachtree Industrial and Level Creek Road. TriScapes, the city’s contractor is working to grade the shoulders and get any remaining disturbed areas stabilized with mulch. One other key milestone achieved in the last week of the month is the delivery of Bridge …...Read More →Public Projects Construction Update – March 2022
PLANNING AND DEVELOPMENT Permits/Inspections. Four single family home permits were issued this month, averaging 3,118 square feet each. The CO was issued for Cantina Loca in February and the restaurant is now officially part of the downtown landscape. A variance application was received during the month of February. VAR-22-001 is a stream buffer variance submitted …...Read More →Management Report – March 2022
PLANNING AND DEVELOPMENT Permits/Inspections. Thirteen new home permits were issued this month, all of which were in the Northmark Subdivision. Eight of those were for townhomes, averaging 2,469 square feet and five were for single-family detached homes, averaging 3,207 square feet each. Permanent signage for The Local and Cantina Loca have been installed. The restaurant …...Read More →Management Report – February 2022
Sugar Hill Greenway TriScapes Construction (TSI) is making progress during the drier weeks of January on the segment of trail between Peachtree Industrial and Level Creek Road. Paving is set to get underway later in February or early March, depending on temperatures as this section is composed of asphalt concrete pavement. Short supplies, short …...Read More →Public Projects Construction Update – January 2022